Indian Trace Roadway Improvements

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

Surtax - West - 192/193 Construction

Indian Trace Road lined with trees

PROJECT DESCRIPTION

The project limits are the Indian Trace corridor from Saddle Club Road east to the City limits at I-75. Improvements will include modification of existing roadway drainage; milling and resurfacing, new 7’ buffered bike lanes, new crossing guard parking at the Saddle Club Road and Indian Trace intersection, accessible curb cut ramps at all existing intersections, accessible sidewalks; signage and landscaping.

PROJECT HIGHLIGHTS

Estimated Cost:   $3,116,600

Benefits:
This roadway is in need of resurfacing. The City of Weston is using this opportunity to add buffers to the existing bike lanes to improve safety, and addressing two areas that are prone to standing water following intense rain events.

Status:  Contract executed

Traffic Impacts:   Lane closures within the project limits with access to local traffic when contractor is working. 

December 2025 Update:

The contractor (Pedrail) is looking to complete the widening (approximately 2’ on either side of the road) by the end of the month.  The widening that is remaining on Indian Trace is from Palm Blvd. to the entrance at Emerald Isle.  Other work remaining within the project limits is narrowing of the median island on Town Center Blvd., rebuilding several ADA curb ramps, miscellaneous drainage work, and completion of the new crossing guard parking area at the Saddle Club and Indian Trace intersection.  All of this work is schedule to be completed before Dec. 19.  The contractor will not be working from Dec. 19 through the holidays and will return to work on January 5, 2026.  In the second week of January the contractor is planning to begin the milling and repaving operations throughout the project limits.   The work will be completed during the day with periodic lane closures.  

For a detailed article on the project and continuing roadway updates, visit NEWS on Indian Trace Roadway 

 

CONTRACTOR:   Pedrail Systems, LLC

CONSULTANT:  EAC Consulting, Inc.

SCHEDULE:
Construction to Start:  March 2025
Anticipated Completion:  December 2025

CONTACT

Scott Buck, P.E., Senior Project Manager
Phone: 954-385-2600
Email

 

Updated12/1/25