Stormwater waterways rehabilitation of Indian Trace Development District that are critical for the City’s flood control. This rehabilitation project will extend service life of critical stormwater waterways and includes the following:

  • Coordination and construction to remove sediment of the City’s waterways within the Indian Trace Development District
  • Remove aquatic vegetation
  • Rebuild ditch bank slopes

BENEFITS

Construction to remove aquatic vegetation, dredging to clear the City’s flood control waterways of sediments and rebuilding of ditch slopes provide resiliency to mitigate anticipated increase in frequency and intensity of future flood events.

LOCATIONS

  1. Ditch No. 5 west of Savanna from SR 84 and south to Regional Park
  2. Ditch No. 3 west of Isles of Weston from Manatee Drive and south to C-11 Canal

Map of the Ditch numbers 3 and 5 project areas

 

 

 

 

 

 

 

 

 

 

 

 

 

COST

Estimated at $1,043,934

STATUS
Construction in progress

SCHEDULE
Construction start: November 2025
Anticipated completion:  September 2026
See detailed schedule below for each Ditch. 

TRAFFIC IMPACTS
None

CONTRACTOR
BDI Marine Contractors, LLC

CONSULTANT
In-house

CONTACT
Jose Casio, Public Works Engineer
Phone: 954-385-2600
Email

Work Hours
Schedule
Scope of Work