Description:

Construction of a new Stormwater System to separate municipal and private systems. The project is located on Blatt Boulevard from Racquet Club Road to east of Hemingway Drive. The project includes the installation of approximately 1,780 linear feet of new drainage pipes and 16 catch basin structures.

Project Estimated Cost:  $304,490.00

Traffic Impacts:  Lane closures within the project limits are anticipated, with access to local traffic when the contractor is working.

Project Benefits:  Establishing a separate municipal stormwater system to eliminate maintenance conflicts and the need for flowage easements.  

Project area map: below