Dates are estimates only, and may be subject to change
due to contractual obligations and/or weather delays.
| Traffic Signal |
| Location: |
South Post Road at North Ridge Drive |
| Description: |
Traffice Signal design and installation |
| Phase: |
|
| Completion: |
The design work for the signal has been completed but the City is awaiting signal warrant approval from Broward County Traffic Engineering.
Completion Date: Not applicable |
| Traffic Signal |
| Location: |
Weston Road at Meridian Parkway |
| Description: |
Traffice Signal design and installation |
| Phase: |
|
| Completion: |
The design work and permitting for the signal will be initiated in May 2012. Construction is anticipated to begin in August 2012
Completion Date: October 2012 |