City of Weston Home Page
Development Services
 
Roadways
Dates are estimates only, and may be subject to change
due to contractual obligations and/or weather delays.

LED Street Light Energy Conservation Program
Location: City owned street lights on public roadways in the City
Description:

LED lighting to replace current lights to save energy/costs by 50%-70%. The City is utilizing a $594,600 Energy Efficiency Conservation Block Grant to assist with funding. Click to view: VIDEO

Phase:
Design Bid Construction
Completion: Nov. 2011 - This project has been completed.

Traffic Signage Inventory and Replacement
Location: All public roadways in Weston
Description: Design and installation of new traffic signage that is more durable during storm events.  The newly styled signage has been tested to withstand 106 mph winds.
Phase:
Design Bid Construction
Completion:

As of Nov. 2011 - Currently completing Bonaventure Blvd. from the Bonaventure area to the southern City limits and Saddle Club Road from the Bonaventure area west to the Regional Park entrance.

After this, installation will begin on Indian Trace, Lakeview Drive and Racquet Club Road.  Indian Trace the balance of the Bonaventure area will take an additional year to complete.


Indian Trace Acceleration Lane
Location: Indian Trace by San Remo Drive
Description:

Design and construction of new acceleration lane to ease traffic coming out of Eagle Point Elementary School to San Remo Drive.

Phase:
Design Bid Construction
Completion: Construction is anticipated to begin in May 2012 with completion in September 2012.

Weston Road Repaving
Location:

The City limits of Weston Road, which are approximately just north of Griffin Road to near Saddle Club Road.

Description:

Design, survey, permitting and construction � Repairs and repaving

Phase:
Design Bid Construction
Completion:

Project design to begin in January 2012 and paving completion anticipated for late July/early August 2012. Construction/paving is anticipated to begin in May 2012


Royal Palm Boulevard Repaving

Location:

From Weston Road going west to Saddle Club Road

Description:

Design, survey, permitting and construction � Repairs and repaving

Phase:
Design Bid Construction
Completion:

Project design to begin in March 2012 and paving completion anticipated for late September/early October 2012. Construction/paving is anticipated to begin July 2012.

 

  Back