Dates are estimates only, and may be subject to change
due to contractual obligations and/or weather delays.
Updated May 2009
|
| Bonaventure Master Plan |
| The Bonaventure Master Plan project is comprised of Phases I, II, III and IV. These infrastructure improvements are funded by the Bonaventure Development District. |
|
| Phase V |
| Location: |
Bonaventure area
of Weston |
| Description: |
Traffic calming
(pavers) at Lakeview Dr. & Saddle Club and Bonaventure Blvd. &
Saddle Club. Entry features at Weston Rd. & Blatt Blvd. and S.R.
84 & Bonaventure Blvd. Racquet Club Rd. drainage improvements,
from Gable Blvd. to Riviera Circle. Miscellaneous drainage
improvements to various areas of Bonaventure. Swale improvements
to Blatt Blvd., Saddle Club Rd. and Lakeview Dr. Hedges along
all main public rights-of-way (requires easements). |
| Phase: |
|
| Completion: |
Substantially
complete |
|
| |
| BDD Pump Stations |
| Location: |
On the south side of St. Rd. 84 with discharge pipes under I-75 to the North New River Canal |
| Description: |
Two new pump stations will replace two 30-year old stormwater pump stations that transfer water from the city's closed canal system to the SFWMD's North New River Canal . They provide flood control for the residents and businesses located in the Bonaventure basin area. The pumps will be housed in new buildings to protect the engines, generator and ancillary equipment. The City has received two grants so far to assist in funding this multi-million dollar project. |
| Phase: |
|
| Completion: |
November 2009 |
|
|
 |
|
|
|